Web-based CompTIA Project+ Certification Exam (PK0-005) practice exam is a convenient format to evaluate and improve preparation for the exam. It is a PK0-005 browser-based application, which means you can access it from any operating system with an internet connection and a web browser. Unlike the desktop-based exam simulation software, the CompTIA Project+ Certification Exam (PK0-005) browser-based practice test requires no plugins and software installation.
CompTIA PK0-005 (CompTIA Project+ Certification) certification exam is a globally recognized certification that validates the knowledge and skills required for managing and completing projects within an organization. CompTIA Project+ Certification Exam certification is designed to assess the project management proficiency of IT professionals and non-IT professionals alike. CompTIA Project+ Certification Exam certification exam is ideal for those individuals who are interested in pursuing a career in project management.
Don't Miss Golden Opportunity – Download CompTIA PK0-005 Dumps Now at Affordable Rates
If you are craving for getting promotion in your company, you must master some special skills which no one can surpass you. To suit your demands, our company has launched the PK0-005 exam materials especially for office workers. For on one hand, they are busy with their work, they have to get the PK0-005 Certification by the little spread time. On the other hand, it is not easy to gather all of the exam materials by themselves. So our PK0-005 study questions are their best choice.
CompTIA PK0-005 (CompTIA Project+ Certification) exam is a globally recognized certification for project managers. CompTIA Project+ Certification Exam certification is designed to validate the skills and knowledge required to manage and complete projects successfully. PK0-005 exam covers a range of project management principles and practices, including project planning, execution, control, and closure, as well as communication, risk management, and stakeholder management. It is an ideal certification for individuals who want to demonstrate their ability to manage projects effectively and efficiently, regardless of industry or organization.
CompTIA Project+ Certification Exam Sample Questions (Q156-Q161):
NEW QUESTION # 156
During a gate review meeting, the deliverable was rejected by the customer.
INSTRUCTIONS
Review the dashboard.
* Part 1: Drag and drop each task, placing them in the correct order based on the project change control process.
* Part 2: Select the proper document(s) to be updated.
If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.
Part 1:
Part 2:
Answer:
Explanation:
See the Explanation for the solution.
Explanation:
Part 1:
Change Control Process:
Consult the RACI matrix.
Define new requirements and record changes.
Assess the schedule, risk, and cost.
Perform a demonstration.
Obtain a sign off.
Update and test the deliverable.
Make an announcement on the company portal.
The change control process is a sequence of steps that helps to manage and document any changes or modifications to a project scope, schedule, cost, quality, or resources. The change control process typically involves the following steps:
Consult the RACI matrix. A RACI matrix is a tool that defines and clarifies the roles and responsibilities of each team member for each task or activity in a project. RACI stands for responsible, accountable, consulted, and informed. Consulting the RACI matrix can help to identify who needs to be involved or informed about the change request and how to communicate with them.
Define new requirements and record changes. The new requirements and changes are the details of what needs to be modified or added to the project deliverables or objectives based on the customer feedback or request. Defining and recording the new requirements and changes can help to communicate and justify the need and rationale for the change and its implications on the project scope and quality.
Assess the schedule, risk, and cost. The schedule, risk, and cost are the aspects of the project that may be affected by the change request. Assessing the schedule, risk, and cost can help to determine the impact and feasibility of the change and identify any possible alternatives or corrective actions to minimize or avoid its negative effects.
Perform a demonstration. A demonstration is a presentation or show of how the modified or updated deliverable works or meets the customer expectations or requirements. Performing a demonstration can help to validate and verify that the change request has been implemented correctly and effectively and to obtain feedback or approval from the customer or stakeholders.
Obtain a sign off. A sign off is a formal acceptance and approval of the change request and its deliverables from the customer or stakeholders. Obtaining a sign off can help to confirm that the change request has been completed successfully and satisfactorily and to close the change control process.
Update and test the deliverable. The deliverable is the product or service that is produced or provided by the project. Updating and testing the deliverable can help to ensure that it meets the quality standards and criteria and that it works as expected after implementing the change request.
Make an announcement on the company portal. The company portal is a platform or channel that allows internal communication and collaboration among employees within an organization. Making an announcement on the company portal can help to inform and update other team members or departments about the change request and its outcomes and to share any lessons learned or best practices from the change control process.
Part2:
Risk register: A risk register is a document that identifies, analyzes, and records the potential risks or uncertainties that may affect a project. Updating the risk register can help to capture any new or modified risks that may arise from the change request and to plan and implement appropriate risk responses.
Schedule: A schedule is a document that shows the planned start and end dates, durations, dependencies, and progress of each task or activity in a project. Updating the schedule can help to reflect any changes or adjustments to the project timeline or milestones that may result from the change request and to monitor and control the project performance and delivery.
Statement of work: A statement of work (SOW) is a document that defines the scope, deliverables, schedule, and terms and conditions of a project or contract. Updating the SOW can help to document any changes or additions to the project scope or deliverables that may be requested or agreed upon by the customer or stakeholders and to ensure alignment and agreement on what needs to be done and how it will be done.
Change log: A change log is a document that tracks and records any changes or modifications that are made to the project scope, schedule, cost, quality, or resources during a project. Updating the change log can help to document the change request, approval, implementation, and impact of each change and ensure traceability and transparency.
NEW QUESTION # 157
After a product is released for production, a tester performs a test to ensure its basic functionality is working as
expected. Which of the following is the tester performing?
- A. Smoke test
- B. Regression test
- C. Penetration test
- D. Stress test
Answer: A
NEW QUESTION # 158
A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?
- A. Formal
- B. Asynchronous
- C. Synchronous
- D. Informal
Answer: C
Explanation:
The project manager should use synchronous communication methods if they prefer to have immediate contact with team members. Synchronous communication is a type of communication that occurs in real time and allows for faster response times and more interactive discussions. Examples of synchronous communication methods include phone calls, video conferences, instant messaging, and face-to-face meetings. Synchronous communication can help to build rapport, clarify doubts, and resolve issues quickly among team members.
Synchronous communication should be used when the project manager prefers to have immediate contact with team members. Synchronous communication allows for real-time interaction and feedback, enabling faster response times and more interactive discussions. References: CompTIA Project+ Study Guide Section
3.1.3
NEW QUESTION # 159
A project implementation partner and the project manager disagree about completed requirements. The project manager shows the project requirements as 70% complete. The implementation partner validates that all requirements were completed. Which of the following would clarify what the project implementation partner was contractually expected to complete?
- A. WBS
- B. SOW
- C. RFI
- D. RFQ
Answer: B
Explanation:
The statement of work (SOW) would clarify what the project implementation partner was contractually expected to complete after disagreeing with the project manager about completed requirements. A SOW is a document that defines the scope, deliverables, schedule, and terms and conditions of a project or contract. A SOW typically includes information such as purpose, scope of work, location of work, period of performance, deliverables schedule, applicable standards, acceptance criteria, special requirements, and payment schedule. A SOW can help to establish a common understanding and agreement between the client and the service provider on what needs to be done and how it will be done.
NEW QUESTION # 160
Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?
- A. Forcing
- B. Compromising
- C. Smoothing
- D. Collaborating
Answer: C
Explanation:
Smoothing is a conflict resolution technique that involves emphasizing the areas of agreement and minimizing the areas of difference. It is useful when the conflict is minor and the relationship between the parties is more important than the issue. Smoothing can help maintain harmony and avoid further escalation of the conflict1.
NEW QUESTION # 161
......
PK0-005 Knowledge Points: https://www.lead2passed.com/CompTIA/PK0-005-practice-exam-dumps.html
- Excellent Updated PK0-005 CBT, Ensure to pass the PK0-005 Exam ???? Simply search for 《 PK0-005 》 for free download on ( www.pass4leader.com ) ????PK0-005 Valid Study Notes
- PK0-005 Training Pdf ???? PK0-005 Online Exam ???? Reliable PK0-005 Braindumps ???? Immediately open ➥ www.pdfvce.com ???? and search for ( PK0-005 ) to obtain a free download ????Reliable PK0-005 Braindumps
- 100% Pass Quiz Updated PK0-005 - Updated CompTIA Project+ Certification Exam CBT ???? Download ✔ PK0-005 ️✔️ for free by simply entering { www.examsreviews.com } website ????Valid PK0-005 Practice Questions
- Updated PK0-005 CBT - 2025 CompTIA First-grade PK0-005 Knowledge Points Pass Guaranteed ???? Search for ( PK0-005 ) and download exam materials for free through “ www.pdfvce.com ” ????New PK0-005 Dumps Ppt
- New PK0-005 Test Pattern ???? PK0-005 Exam Cram Questions ♣ PK0-005 Latest Test Labs ???? Easily obtain free download of ▶ PK0-005 ◀ by searching on [ www.dumpsquestion.com ] ????PK0-005 Online Exam
- Exam PK0-005 Dumps ???? PK0-005 Valid Mock Exam ???? PK0-005 Clear Exam ???? Download ⮆ PK0-005 ⮄ for free by simply searching on ( www.pdfvce.com ) ????PK0-005 Valid Mock Exam
- PK0-005 Free Download Pdf ???? Exam PK0-005 Dumps ???? PK0-005 Training Pdf ???? Go to website 《 www.getvalidtest.com 》 open and search for ⇛ PK0-005 ⇚ to download for free ????PK0-005 Latest Study Guide
- 100% Pass Quiz CompTIA - Efficient PK0-005 - Updated CompTIA Project+ Certification Exam CBT ???? Open website ⮆ www.pdfvce.com ⮄ and search for ➤ PK0-005 ⮘ for free download ????PK0-005 Valid Study Notes
- Updated Updated PK0-005 CBT - Easy and Guaranteed PK0-005 Exam Success ???? Copy URL ⇛ www.prep4pass.com ⇚ open and search for 「 PK0-005 」 to download for free ????PK0-005 Free Download Pdf
- 100% Pass Quiz Updated PK0-005 - Updated CompTIA Project+ Certification Exam CBT ???? Go to website ⇛ www.pdfvce.com ⇚ open and search for ( PK0-005 ) to download for free ????Valid Braindumps PK0-005 Free
- PK0-005 Vce Files ???? PK0-005 Valid Mock Exam ???? PK0-005 Online Exam ???? Search for ➥ PK0-005 ???? and download it for free immediately on ☀ www.examdiscuss.com ️☀️ ????PK0-005 Clear Exam
- PK0-005 Exam Questions